How Long Does an Attic Conversion Take?
On site, a standard roof-window (Velux) attic conversion takes 2 to 4 weeks (10 to 20 working days). Adding an en-suite adds 3 to 5 days.
Week-by-week schedule on site, when the stairs break-through happens, and lead times before work starts.
Free, no obligation. One attic conversion company covering your county prices it, not five.
- 2 to 4 wksstandard Velux conversion on site
- 4 to 6 wksrear or side dormer conversion
- 6 to 10 wkship-to-gable conversion
- Day 8–10when the landing ceiling is opened for the stairs
Week-by-week schedule for a standard 3-week Velux conversion
| Stage | Days on site | What happens in your house |
|---|---|---|
| Week 1 — Steel, floor joists & tank move | Days 1 to 5 | Water tank relocated into the eaves, padstones and steel RSJs fitted, independent floor joists laid and structural subfloor screwed down. |
| Week 2 — Roof windows, insulation & stairs opening | Days 6 to 10 | Velux escape windows fitted from inside, rafters and dwarf walls insulated to 0.25 U-value, first-fix electrics/plumbing, and the landing ceiling opened for the new stairs. |
| Week 3 — Plasterboard, skim, fire doors & second fix | Days 11 to 15 | Fire-rated plasterboard and skim coat, custom staircase balustrades, self-closing FD20 fire doors on the bedrooms below, skirting, sockets, linked alarms and engineer's final inspection. |
Every attic conversion type and rule explained
Costs, the July 2026 dormer and rooflight exemptions, Building Regulation fire safety and structural steel.
Habitable Velux conversionsBedroom or study inside the existing roof slope (€20,000 to €35,000), with fixed fire-protected stairs and compliance cert.Velux vs dormer guide →
Rear & side dormers (Class 1B)Full standing height and floor space (€28,000 to €45,000); exempt up to 30 m³ since 27 July 2026 under S.I. No. 344 of 2026.Dormer prices & rules →
Hip-to-gable conversionsExtends a sloping side hip into a vertical gable wall (€35,000 to €55,000+) so your new stairs can rise along the side.Hip-to-gable guide →
2026 planning exemptionsSide/rear dormers ≤ 30 m³ (Class 1B) and up to 2 front rooflights ≤ 100×90 cm (Class 1C) explained in plain English.2026 planning rules →
Building Regs & fire doorsLoft Conversion Guidelines 2022: TGD B fire doors, escape windows, TGD K stairs and the 2.4 m height rule.Building Regs guide →
Adding an en-suite bathroomWhere the soil pipe runs, boosted water pressure and placing the shower under the highest part of the ridge (+€5,000 to €8,000).En-suite cost & layout →Real examples and installation detail


Get a fixed attic conversion price with no obligation
Tap the kind of conversion, your house type and your county. Your request goes to one attic conversion company that covers your county, and they ring you to arrange a free loft survey and written quote.
Attic Conversion Cost guides & price breakdowns
Straight answers to what people ask most: itemised costs, specifications, planning or grants, and what to check before you book.
More guides & resources: All guides & calculator hub · Technical & trade glossary · Frequently asked questions · All areas covered · About this site
Questions people ask
Do we have to move out of the house during an attic conversion?
No. For the first 70% of a roof-window conversion, the builders work entirely inside the roof space (entering through the attic hatch or scaffold) while your house below stays sealed off. The messy two days are when the landing ceiling is opened to fit the new staircase towards the end of week two.
How long is the wait before an attic company can start?
Most reputable Irish attic specialists book 4 to 8 weeks ahead. If your conversion is a Class 1B rear dormer or Class 1C roof-window job, no planning wait is needed; if you need full planning permission for a hip-to-gable or front dormer, allow 8 to 12 weeks for the council decision first.
Attic Conversion Cost across all 26 counties
Requests from all 26 counties go to one local specialist who covers your county — from Dublin, Cork, Galway and Limerick to Kildare, Meath, Wicklow, Waterford and Donegal. Pick your county below for local prices, specifications and advice. Compare all areas covered →
Get a fixed written quote for your attic conversion
One specialist covering your county checks your ridge height, roof structure and stairs landing, and gives you a written price.