How Long Does an Attic Conversion Take?

On site, a standard roof-window (Velux) attic conversion takes 2 to 4 weeks (10 to 20 working days). Adding an en-suite adds 3 to 5 days.

Week-by-week schedule on site, when the stairs break-through happens, and lead times before work starts.

Free, no obligation. One attic conversion company covering your county prices it, not five.

  • 2 to 4 wksstandard Velux conversion on site
  • 4 to 6 wksrear or side dormer conversion
  • 6 to 10 wkship-to-gable conversion
  • Day 8–10when the landing ceiling is opened for the stairs

Week-by-week schedule for a standard 3-week Velux conversion

StageDays on siteWhat happens in your house
Week 1 — Steel, floor joists & tank moveDays 1 to 5Water tank relocated into the eaves, padstones and steel RSJs fitted, independent floor joists laid and structural subfloor screwed down.
Week 2 — Roof windows, insulation & stairs openingDays 6 to 10Velux escape windows fitted from inside, rafters and dwarf walls insulated to 0.25 U-value, first-fix electrics/plumbing, and the landing ceiling opened for the new stairs.
Week 3 — Plasterboard, skim, fire doors & second fixDays 11 to 15Fire-rated plasterboard and skim coat, custom staircase balustrades, self-closing FD20 fire doors on the bedrooms below, skirting, sockets, linked alarms and engineer's final inspection.

Real examples and installation detail

Irish 3-bed semi-detached house suitable for a Velux or hip-to-gable attic conversion
Hip-to-Gable · €35k–€55k+. 3-bed semi-detached hip-to-gable conversion (€35,000 to €55,000+) extending the sloping side hip into a vertical gable wall.
Bright habitable bedroom window meeting TGD Part B fire escape rules
Part B Fire Escape Spec. Part B fire escape and glazing: minimum 0.33 m² clear opening (450x450 mm) and 600–1,100 mm sill height for bedroom certification.

Get a fixed attic conversion price with no obligation

Tap the kind of conversion, your house type and your county. Your request goes to one attic conversion company that covers your county, and they ring you to arrange a free loft survey and written quote.

What kind of attic conversion?

Pick the closest match.

Questions people ask

Do we have to move out of the house during an attic conversion?

No. For the first 70% of a roof-window conversion, the builders work entirely inside the roof space (entering through the attic hatch or scaffold) while your house below stays sealed off. The messy two days are when the landing ceiling is opened to fit the new staircase towards the end of week two.

How long is the wait before an attic company can start?

Most reputable Irish attic specialists book 4 to 8 weeks ahead. If your conversion is a Class 1B rear dormer or Class 1C roof-window job, no planning wait is needed; if you need full planning permission for a hip-to-gable or front dormer, allow 8 to 12 weeks for the council decision first.

Attic Conversion Cost across all 26 counties

Requests from all 26 counties go to one local specialist who covers your county — from Dublin, Cork, Galway and Limerick to Kildare, Meath, Wicklow, Waterford and Donegal. Pick your county below for local prices, specifications and advice. Compare all areas covered →

Get a fixed written quote for your attic conversion

One specialist covering your county checks your ridge height, roof structure and stairs landing, and gives you a written price.